Progress on site update November 2009

The Adamstown Project Team monitors progress on site on a regular basis to ensure that development is taking place in accordance with the details of the planning permissions and compliance submissions.

The Adamstown Project Team monitors progress on site on a regular basis to ensure that development is taking place in accordance with the details of the planning permissions and compliance submissions. Please contact Derek Taylor of the Adamstown Project Team ( dtaylor@sdublincoco.ie or phone 01 414900) if you have any queries or concerns about any aspect of the works taking place on site.

1. Residential Development

To date permission has been granted for 3428 residential units within the Adamstown SDZ lands under seven separate planning permissions as identified below.

Table 1: Residential development to date within Adamstown

Development

Total Residential Units Permitted

Units Started

Units Substantially Completed (not yet ready for occupation)

Units Occupied

Adamstown Castle 1

(SDZ04A/1)

407

407

7

400

Airlie Stud

The Paddocks 1

(SDZ05A/2)

252

252

12

243

Adamstown Castle 2

(SDZ06A/3)

166

166

18

148

Adamstown Square 1

(SDZ06A/6)

174

174

166

Adamstown Creche (SDZ06A/7)

7

7

7

0

Adamstown Castle Landmark Site

(SDZ06A/12)

50

40

0

0

Adamstown Square 2

(SDZ06A/13)

224

176

80

72

Adamstown Square 2 Amendments

(SDZ07A/0004)

38

38

38

0

Airlie Stud

The Paddocks 1b

(SDZ07A/0001)

143

99

17 

61

St Helens

Phase 1

(SDZ07A/0007)

374

20

20

0

Adamstown Square 3

(SDZ07A/0011)

328

0

0

0

Somerton Phase 1

(SDZ07A/0012)

192

0

0

0

Adamstown DC Phase 1

(SDZ08A/0002)

597

0

0

0

Adamstown Square 4

(SDZ08A/0006)

39

0

0

0

Airlie Stud

The Paddocks 2a

(SDZ08A/0005)

121

0

0

0

Tobermaclugg Village

Phase 1

(SDZ08A/0004)

316

0

0

0

Totals

3428

1379

208

1097

Adamstown Castle Development Area

All of the residential units withinthe Adamstown Castle 1 and Adamstown Castle 2 developmentshave now been completed and the majority of residential units are now occupied.

Work has continued to progress well on the Admstown Castle Landmark (Sentinal site) and the first convenience store has now been opened which is soon to be followed by a cafe scheduled for opening at the end of 2009.

Summary of Residential Development to date within the Adamstown Castle Development Area

Units Granted

Units Started

Units substantially completed (not yet ready for occupation)

Units Occupied

630

620

25

555

All of the residential units within the ‘Paddocks’ development (Phase 1a) have now been completed and the majority of residential units are now occupied.

Development works has continued to progress well on the second phase of development with the ‘Paddocks’. The first residential units within (Phase 1b) have now been occupied and there are a number of residential units coming towards completion which are expected to be completed and occupied over the coming months.

Summary of Residential Development to date within the Paddocks - Airlie Stud Development Area

Units Granted

Units Started

Units substantially completed (not yet ready for occupation)

Units Occupied

518

351

37

304

Adamstown Square Development Area

All of the residential units within Adamstown Square 1 development have now been completed and the majority of residential units are now occupied.

Adamstown Square 2 development consists of a further 262 residential units. Blocks 2 and 3 have now been completed and to date approx half of the residential units within these blocks have been occupied with the remaining units expected to be occupied over the coming months.

Summary of Residential Development to date within the Adamstown Square Development Area

Units Granted

Units Started

Units substantially completed (not yet ready for occupation)

Units Occupied

803

388

126

238

St Helens Development Area

A small number of residential units within the first phase have now been substantially completed. These units are intended to form the show court area for St Helens.

Summary of Residential Development to date within the St Helen’s Development Area

Units Granted

Units Started

Units substantially completed (not yet ready for occupation)

Units Occupied

374

20

20

0

(See attached chart for overview of delivery of residential development to date)

Adamstown Castle Public Park

Works within the Public Park located within the Adamstown Castle development have been completed.

2.Provision of Infrastructure

Table 2 : Infrastructural development to date within Adamstown

Development

Status

Phasing

Scheduled for Completion

Adamstown Link Rd

(SD04A/0964)

Commenced Construction

October 2005

Required as haul road for Phase 1a –

Required as two way single carriageway for

Phase 1b

Currently being used as haul road for all construction related traffic and QBC for 151 Bus Route

Adamstown Railway Station

(SDZ04A/2)

Commenced Construction

February 2006

Phase 1b Requirement

Adamstown Railway Station and Park & Ride now open.

Adamstown Primary Schools

(SDZ06A/2)

Commenced Construction

August 2006

Phase 2 Requirement

Both Primary Schools are now occupied.

Tobermaclugg Pumping Station

(SDZ06A/4)

Commenced Construction August 2007

Phase 3 Requirement

Completed and currently under going final testing.

Strategic Roads Application

(SDZ06A/5)

Commenced Construction

October 2006

Various roads required within various Phases

Loop Rd 1 – Completed to Haul Road Standard.

Adamstown Castle Creche (SDZ06A/7)

Commenced Construction

November 2006

Phase 1a Requirement

Adamstown Castle Creche (Giraffe Childcare) is now open.

Adamstown Post Primary School

(SDZ07A/0002)

Commenced Construction

April 2008

Phase 4 Requirement

Completed September 2009 - now occupied

Newcastle Rd R120 upgrade works

The associated roadwork’s are now complete both of the new signal controlled junctions along the Newcastle rd, one at the Adamstown Castle junction and one at the Tandy’s Lane junction, are now fully operational.

Adamstown Link Road (ref: SD04/0964)

The Adamstown Link continues to be used as the main access route for all construction traffic accessing the Adamstown Castle development area, helping to remove much of the construction traffic related to the Adamstown Development from the R120 Newcastle Rd.(ref: SDZ04A/2)

The new Adamstown Railway Station and Park & Ride opened in April 2007.

Adamstown Primary School (ref: SDZ06A/2)

Both Primary school buildings, containing 16 classrooms, have been completed and are now fully operational.

Adamstown Creche (SDZ06A/7)

The first crèche facility, Adamstown Castle Creche, has been completed and is currently being operated by Giraffe Childcare.

Adamstown Post Primary School (ref: SDZ07A/0002)

The secondary school building consisting of 63 classrooms, 25 guidance, pastoral, multifunctional rooms and a library has now been completed and is fully operational.

3. Planning Applications

Over the last month South Dublin County Council has received no further planning application for development within Adamstown.

Full details of the above planning applications and any additional planning applications to date within Adamstown are available for viewing within the Planning Applications section of this site. [Click here]